BER Information BER is the acronym for Building Education Revolution which is a $3 million federal government grant our school has been given to build a new building that will consist of 6 learning spaces and other shared areas. To see a plan of the new building click here. During the construction of this great new building we have been given portable classrooms and other buildings to use. For more information about this click here.
Progress Report Work began with the removal of the mound and all of the play equipment on Monday June 1st. See the pics below.
On Thursday June 4th the first of our portables arrived and was craned into place where the old play equipment used to be. See pics below.
On June 9th and 10th two portables and our new canteen were delivered and craned into place, see the pics below.
After a few delays we have finally got back on track with the demolition of the library and the old prep rooms.
|
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||